303.02
Rehabilitation Reserve Agreement
Requirements
You must ensure that the Borrower BorrowerPerson who is the obligor per the Note. :
- Executes a Modifications to Multifamily Loan and Security Agreement (Rehabilitation Reserve – Moderate Rehabilitation) ( Form 6222
) that identifies the planned scope of the Rehabilitation Work
Rehabilitation WorkAggregate repairs, replacements, or improvements (including all Completion/Repairs) required to be performed and completed within a specified time period after the Mortgage Loan Origination Date for a Moderate Rehabilitation Property.
on the Rehabilitation Work Schedule, including
- all of the Rehabilitation Work Rehabilitation WorkAggregate repairs, replacements, or improvements (including all Completion/Repairs) required to be performed and completed within a specified time period after the Mortgage Loan Origination Date for a Moderate Rehabilitation Property. items,
- estimated costs,
- allowance for cost overruns, and
- completion dates.
- Completes a budget for the planned Rehabilitation Work Rehabilitation WorkAggregate repairs, replacements, or improvements (including all Completion/Repairs) required to be performed and completed within a specified time period after the Mortgage Loan Origination Date for a Moderate Rehabilitation Property. .
- Funds a Rehabilitation Reserve Account
Rehabilitation Reserve AccountCustodial Account established by the Lender and funded by deposits from the Borrower per the Rehabilitation Reserve Agreement to fund the Rehabilitation Work.
with the:
- entire budgeted amount (or a higher amount that you require) for all Rehabilitation Work Rehabilitation WorkAggregate repairs, replacements, or improvements (including all Completion/Repairs) required to be performed and completed within a specified time period after the Mortgage Loan Origination Date for a Moderate Rehabilitation Property. that is not identified as Completion/Repairs Completion/RepairsRepairs or capital item replacements and deferred maintenance: identified per the Property Condition Assessment; and required per the Completion/Repair Schedule, or Completion/Repair Agreement. by the PCA PCAAssessment of the Property's physical condition and historical operation. ; and
- estimated cost (or a higher amount that you require per Part II, Chapter 4: Lease Audits, Inspections, and Reserves, Section 405: Completion/Repairs ) for Completion/Repairs Completion/RepairsRepairs or capital item replacements and deferred maintenance: identified per the Property Condition Assessment; and required per the Completion/Repair Schedule, or Completion/Repair Agreement. .